rép COMMUNITY ENTERPRISE             Exhibit 1      
  PROJECT PLAN              
  Phase 2 : January to December 2008   BUDGET    
Establish First Center , Build 10 houses, Industry Center & Community Center at Nerkundrapattu
                       
  Task   Start Date Duration   Labor Materials Equipment Other   Total Cost
PREPARATION     8 weeks              
January 1 to February 28, 2008
  Replace molds & construct molds for new panels   Jan 07 5 weeks       2,500
  2,500
  Purchase equipment: Generator, tools   Jan 07 1 weeks       3,500
  3,500

Purchase vehicle   Jan 01 3 weeks       5,000
  5,000
  Travel   Jan 19 3 weeks         3,500   3,500
Subtotal: Preparation






11,000 3,500
14,500












PHASE 2









March 1 to December 31, 2008









  Purchase site near Pudupattinam   Feb 15 2 weeks         40,000   40,000

Clear land
Mar 01 1 week
500



500

Dig wells & install pumps
1-Mar 2 weeks
200 1,000


1,200
  Build fences   Mar 01 4 weeks   500 1,000  
  1,500
  Install septic tanks   Mar 01 4 weeks   400 1,500  
  1,900
  Create access ways/roads on property   Mar 07 4 weeks   500 1,500

  2,000

Install electrical supply   Mar 14 2 weeks   100 600  
  700

Set out foundations for houses, Industry center and Community center   Mar 21 2 weeks   200    

200
SUBTOTAL: Land & Site Prep
        2,400 5,600
40,000   48,000













Order steel for Industry Center roof
1-Feb 1 week

1,500


1,500

Purchase materials for Industry center
1-Feb 1 week

2,500


2,500

Cast wall panels & roof panels for Industry Center
14-Feb 4 weeks
500 1,500
1,000
3,000

Order steel for roofs of First 5 houses
21-Mar 1 week

2,500


2,500

Order sand, crushed stone & rebar for First 5 houses
21-Mar 1 week

2,500


2,500

Set out & dig foundations for Industry Center
25-Mar 1 week
200

1,000
1,200

Cast foundations for Industry Center
1-Apr 1 week
200



200

Construct Industry Center
15-Apr 4 weeks
300 300


600
Subtotal - Industry Center




1,200 5,800
2,000
9,000













Assemble prototype molds for new products: Fencing posts, pillars, doors, fixtures etc.
25-Mar 4 weeks
200 800


1,000

Pursue contracts for Community products: Wall panels, roof panels, fencing posts, pillars, doors, flooring, counter tops etc.
1-Feb Ongoing
500

1,000
1,500

Set up production facilities in Industry Center
7-Mar 2 weeks
500 3,000
500
4,000

Train workers
1-Feb Ongoing



1,500
1,500

Manufacture and market Community products
1-Apr Ongoing






Subtotal - Business Development




1,200 3,800
3,000
8,000













Cast wall and roof panels for First five houses
1-Apr 5 weeks
500 1,500


2,000

Set out & dig foundations for 5 houses
21-Mar 2 weeks
500 500


1,000

Cast foundations and pillars for 5 houses
7-Apr 2 weeks
500

500
1,000

Construct 5 houses
21-Apr 2 weeks
1,000 1,000
1,500
3,500
Subtotal - First 5 Houses




2,500 8,000
2,000
12,500













Order steel and materials for Community Center
1-Apr 1 week